Delivering a cement plant expansion by sea and road
An initial 90 TEU import marked the beginning of a much larger logistics partnership. Following a successful first delivery, Röhlig-Grindrod was awarded an extensive cement plant expansion project involving three breakbulk movements over two years. In total, approximately 12,000 tonnes of project cargo travelled from Shanghai, China, through the Port of Durban to the customer’s plant in South Africa. The programme required close control of customs processing, cargo handling, specialist transport and final delivery, with individual pieces weighing up to 80 tonnes.
Project Highlights
| Customer Industry | Cement manufacturing and construction materials |
|---|---|
| Origin | China |
| Destination | South Africa |
| Transport Modes | Sea Freight |
| Teams involved | Italy and South Africa |
| Additional Services | Customs coordination and processing, tallying and surveying, port operations coordination, milestone reporting and final delivery |
| Cargo | Equipment for a cement plant extension |
| Total Weight | Approximately 12,000 tonnes |
| Unit Weight | Up to 80 tonnes per piece |
Project Overview
An industry-leading cement manufacturer was expanding its production facility in South Africa and needed project-critical equipment transported from Shanghai to the plant site.
The relationship began with a Delivered at Place (DAP) shipment of approximately 90 TEU. Röhlig Italy coordinated the international movement, an alternate freight forwarder completed import customs clearance, and Röhlig-Grindrod managed delivery from the port to the site.
The successful execution of this initial assignment demonstrated Röhlig-Grindrod’s operational and project-management capabilities. It led to a significantly larger plant extension contract comprising three breakbulk projects over the following two years.
The Challenge
The plant extension involved a high-volume abnormal breakbulk consignment moving under urgent project timelines. Delivery depended on effective coordination between international freight forwarders, customs authorities, port operators, surveyors, transport providers and the construction site.
The principal challenges included:
- Managing approximately 12,000 tonnes of breakbulk project cargo as a staged consignment.
- Coordinating customs processing and cargo handovers in accordance with the staged consignment ruling granted by Customs & Excise South Africa.
- Protecting oversized equipment, including individual pieces weighing up to 80 tonnes, from damage or loss during discharge and handover.
- Adjusting operational plans in response to inclement weather and disrupted vessel operations.
- Aligning multiple service providers as schedules and project requirements changed.
- Delivering oversized, project-critical equipment during South Africa’s December embargo restriction period.
- Maintaining accurate milestone visibility and consistent communication across all stakeholders.
Any delay at the port, during customs processing or on the final transport leg could have affected the customer’s construction programme.
The Solution
Building on the initial shipment
The initial 90 TEU movement allowed Röhlig-Grindrod to establish a clear operating relationship with the customer and demonstrate its ability to manage the final delivery stage.
For the subsequent plant expansion, the team developed an integrated project logistics plan covering customs processing, cargo control, port handling and transport to the plant.
Coordinated customs processing
Röhlig-Grindrod coordinated the documentation and processing required under the staged consignment ruling. This supported orderly customs clearance and handover as successive cargo stages arrived in South Africa.
Cargo control during discharge
Specialist tally and surveyor services were procured for the offloading operation. Their involvement provided independent cargo records and helped mitigate the risk of damage, shortages or discrepancies at a critical transfer point.
Port-to-site transport management
The team coordinated transport providers and delivery schedules for the movement from Durban to the plant. Particular attention was given to oversized units and project-critical equipment, including pieces weighing up to 80 tonnes.
Plans were continually reviewed to account for weather conditions, vessel disruption and the restrictions affecting abnormal transport during the December holiday period.
Dedicated project oversight
The Röhlig-Grindrod South Africa team maintained central oversight of the local operation. Continuous stakeholder communication and milestone reporting kept the customer and service providers aligned as conditions changed.
This coordinated approach gave the customer a consistent point of control across customs, port operations, specialist services and final delivery.
The Result
Röhlig-Grindrod successfully completed three breakbulk projects over a two-year period, delivering approximately 12,000 tonnes of cement plant equipment to the customer’s site.
The project achieved several important outcomes:
- Critical equipment reached the plant on schedule, supporting the customer’s expansion programme.
- Specialist surveying and tallying reduced the operational risks associated with oversized cargo.
- Customs, port and transport activities were coordinated across multiple service providers.
- Delivery planning adapted to weather disruption, changing vessel operations and seasonal transport restrictions.
- The relationship progressed from an initial 90 TEU assignment into a major plant expansion programme.
- Röhlig-Grindrod strengthened its position as a trusted logistics partner for future industrial and infrastructure projects.
Questions and answers
How was the cement plant equipment transported from China to South Africa?
The project combined containerised and breakbulk sea freight with specialist port-to-site transport. Cargo moved from Shanghai through the Port of Durban before final delivery to the cement plant.
How was customs clearance managed for the staged breakbulk consignment?
Röhlig-Grindrod coordinated customs documentation and processing in accordance with a staged consignment ruling granted by Customs & Excise South Africa. This allowed the cargo to be processed and handed over in successive stages.
How were the risks associated with oversized cargo managed?
The project team procured specialist tally and surveyor services for cargo discharge, coordinated suitable transport providers and maintained dedicated oversight through to final delivery. These controls were particularly important for cargo pieces weighing up to 80 tonnes.
Discover more case studies
-
- Industrial / Manufacturing
Two charter flights keep a supply chain moving
Peru
Bolivia
- Challenge
- Time-critical shipment
- Via
- Air, Charter
-
- Multimodal heavy machinery
Four heavy machines, three transport modes
China
Brazil
- Challenge
- Heavy machinery transport
- Via
- Sea, Road, Air
-
- Aerospace / Aviation
Secure Helicopter Air Freight
Germany
Brazil
- Challenge
- High-value cargo
- Via
- Air