Track & Trace
en
Search
Login
Track & Trace
Languages
Logins

Delivering a cement plant expansion by sea and road

by Röhlig Team last update:

An initial 90 TEU import marked the beginning of a much larger logistics partnership. Following a successful first delivery, Röhlig-Grindrod was awarded an extensive cement plant expansion project involving three breakbulk movements over two years. In total, approximately 12,000 tonnes of project cargo travelled from Shanghai, China, through the Port of Durban to the customer’s plant in South Africa. The programme required close control of customs processing, cargo handling, specialist transport and final delivery, with individual pieces weighing up to 80 tonnes.

Download Case Study

Project Highlights

Customer Industry Cement manufacturing and construction materials
Origin China
Destination South Africa
Transport Modes Sea Freight
Teams involved Italy and South Africa
Additional Services Customs coordination and processing, tallying and surveying, port operations coordination, milestone reporting and final delivery
Cargo Equipment for a cement plant extension
Total Weight Approximately 12,000 tonnes
Unit Weight Up to 80 tonnes per piece

Project Overview

An industry-leading cement manufacturer was expanding its production facility in South Africa and needed project-critical equipment transported from Shanghai to the plant site.

The relationship began with a Delivered at Place (DAP) shipment of approximately 90 TEU. Röhlig Italy coordinated the international movement, an alternate freight forwarder completed import customs clearance, and Röhlig-Grindrod managed delivery from the port to the site.

The successful execution of this initial assignment demonstrated Röhlig-Grindrod’s operational and project-management capabilities. It led to a significantly larger plant extension contract comprising three breakbulk projects over the following two years.

The Challenge

The plant extension involved a high-volume abnormal breakbulk consignment moving under urgent project timelines. Delivery depended on effective coordination between international freight forwarders, customs authorities, port operators, surveyors, transport providers and the construction site.

The principal challenges included:
 

  • Managing approximately 12,000 tonnes of breakbulk project cargo as a staged consignment.
  • Coordinating customs processing and cargo handovers in accordance with the staged consignment ruling granted by Customs & Excise South Africa.
  • Protecting oversized equipment, including individual pieces weighing up to 80 tonnes, from damage or loss during discharge and handover.
  • Adjusting operational plans in response to inclement weather and disrupted vessel operations.
  • Aligning multiple service providers as schedules and project requirements changed.
  • Delivering oversized, project-critical equipment during South Africa’s December embargo restriction period.
  • Maintaining accurate milestone visibility and consistent communication across all stakeholders.

Any delay at the port, during customs processing or on the final transport leg could have affected the customer’s construction programme.

The Solution

Building on the initial shipment

The initial 90 TEU movement allowed Röhlig-Grindrod to establish a clear operating relationship with the customer and demonstrate its ability to manage the final delivery stage.

For the subsequent plant expansion, the team developed an integrated project logistics plan covering customs processing, cargo control, port handling and transport to the plant.

Coordinated customs processing

Röhlig-Grindrod coordinated the documentation and processing required under the staged consignment ruling. This supported orderly customs clearance and handover as successive cargo stages arrived in South Africa.

Cargo control during discharge

Specialist tally and surveyor services were procured for the offloading operation. Their involvement provided independent cargo records and helped mitigate the risk of damage, shortages or discrepancies at a critical transfer point.

Port-to-site transport management

The team coordinated transport providers and delivery schedules for the movement from Durban to the plant. Particular attention was given to oversized units and project-critical equipment, including pieces weighing up to 80 tonnes.

Plans were continually reviewed to account for weather conditions, vessel disruption and the restrictions affecting abnormal transport during the December holiday period.

Dedicated project oversight

The Röhlig-Grindrod South Africa team maintained central oversight of the local operation. Continuous stakeholder communication and milestone reporting kept the customer and service providers aligned as conditions changed.

This coordinated approach gave the customer a consistent point of control across customs, port operations, specialist services and final delivery.

The Result

Röhlig-Grindrod successfully completed three breakbulk projects over a two-year period, delivering approximately 12,000 tonnes of cement plant equipment to the customer’s site.

The project achieved several important outcomes:
 

  • Critical equipment reached the plant on schedule, supporting the customer’s expansion programme.
  • Specialist surveying and tallying reduced the operational risks associated with oversized cargo.
  • Customs, port and transport activities were coordinated across multiple service providers.
  • Delivery planning adapted to weather disruption, changing vessel operations and seasonal transport restrictions.
  • The relationship progressed from an initial 90 TEU assignment into a major plant expansion programme.
  • Röhlig-Grindrod strengthened its position as a trusted logistics partner for future industrial and infrastructure projects.
This project showed how dependable execution on one shipment can build the confidence for a much larger programme. Close coordination across customs, port operations, surveyors and transport providers helped us keep critical plant equipment moving despite changing conditions.
Woman in glasses sitting at an office desk with a laptop, mouse, and world map on the wall
Siveshnie Moodley
Import Manager
Rohlig Grindrod (Pty) Ltd

Questions and answers

How was the cement plant equipment transported from China to South Africa?

The project combined containerised and breakbulk sea freight with specialist port-to-site transport. Cargo moved from Shanghai through the Port of Durban before final delivery to the cement plant.

How was customs clearance managed for the staged breakbulk consignment?

Röhlig-Grindrod coordinated customs documentation and processing in accordance with a staged consignment ruling granted by Customs & Excise South Africa. This allowed the cargo to be processed and handed over in successive stages.

How were the risks associated with oversized cargo managed?

The project team procured specialist tally and surveyor services for cargo discharge, coordinated suitable transport providers and maintained dedicated oversight through to final delivery. These controls were particularly important for cargo pieces weighing up to 80 tonnes.

Discover more case studies

    • Industrial / Manufacturing
    Freight pallets with Röhlig banner, forklift and cargo aircraft on the airport apron

    Two charter flights keep a supply chain moving

    Peru

    Bolivia

    Challenge
    Time-critical shipment
    Via
    Air, Charter

    When an urgent shipment from Lima to Santa Cruz became critical to business continuity, an industrial manufacturer needed a transport plan built around its deadline. Röhlig Bolivia designed and executed two dedicated air charter flights, ensuring the confidential commercial cargo reached its destination safely and on schedule.

    • Multimodal heavy machinery
    Film-wrapped heavy machine is lifted onto a low-loader by crane in the logistics centre.

    Four heavy machines, three transport modes

    China

    Brazil

    Challenge
    Heavy machinery transport
    Via
    Sea, Road, Air

    Moving four exceptionally heavy machines across three countries would demand close coordination under any circumstances. For this project, Röhlig also had to manage crane handling, oversize and overweight road permits across eight US states, in-bond compliance and the exacting requirements of a commercial air service. When damage to the final machine’s wooden platform threatened its planned flight, the team responded over the weekend. A replacement platform was built in less than 48 hours, enabling the cargo to be re-tendered in time for the Wednesday morning departure.

    • Aerospace / Aviation
    Packed air freight on a roller pallet in front of a cargo aircraft on the airport apron

    Secure Helicopter Air Freight

    Germany

    Brazil

    Challenge
    High-value cargo
    Via
    Air

    Transporting a high-value helicopter across continents leaves little room for error. When an aerospace customer needed to move a helicopter from Germany to Brazil, Röhlig developed a carefully coordinated air freight solution that protected the fuselage and associated components throughout the journey. Close cooperation between Röhlig Munich and Röhlig Brazil enabled the teams to manage the specialist handling, regulatory requirements and operational schedule from origin to destination.